|
|
||||
|
COURTS PROVIDE PROTECTION FOR SUBCONTRACTOR IN CLAIMSMain Contract Dispute Subcontractors being lower down the food chain are reliant upon contractors for payment. Where disputes arise over the amount a main contractor is obliged to pay to the subcontractor the usual “ he who alleges must prove ” argument comes to the fore. If the main contractor makes a claim against a subcontractor and as a result reduces the amount due for payment or seeks to recover actual payment from the subcontractor then the shoe is on the other foot. In the case of Bovis Lend Lease Ltd v RD Fire Protection Ltd (2003) a dispute arose concerning a claim from the management contractor Bovis against FD Fire Protection a subcontractor who undertook the dry lining and fire protection. Bovis had been appointed as the management contractor on the Braehead Shopping Centre in Glasgow. A major row broke out between Braehead the developer and Bovis with claims flying in both directions. Bovis alleged that they were owed £37m as the balance due on the final account and damages for breach of contract whilst Braehead counterclaimed in the sum of £ 65.8m in respect of alleged mismanagement, defective work and overvaluation of the works. Proceedings were commenced and as part of the process Bovis joined RD Fire Protection as a joint defendant on the basis that part of the counterclaim related to the quality of work undertaken by RD Fire Protection. Bovis and Braehead entered into a compromise arrangement whereby Braehead paid Bovis a sum of £ 15m in full and final settlement of all matters in dispute which included the alleged defective work carried out by RD. Claim Against the SubcontractorThe settlement reached between Braehead and Bovis was on a global basis in that there was no build up which showed how the amount had been calculated. The cost of correcting the defective work formed part of the counterclaim but it was not clear whether or not the agreed figure included any provision in respect of the alleged defective work. Bovis however claimed from RD Fire Protection the full cost of the remedial works as pleaded by Braehead. They sought to bypass the settlement entirely and proceed as if it had never taken place. This was obviously wrong as Bovis were only entitled to recover whatever loss they could prove resulted from the defective work. It was possible for there to be some provision in the global settlement figure for the defective work the more likely however was that as the settlement figure was on a global basis the sum could not be identified. It was open therefore for Bovis to request the Court to ascertain the sum involved which could then be passed on to RD Fire Protection. Bovis did not use this approach but instead passed on the total sum originally claimed by Braehead. The court rejected the case brought by Bovis and found for RD Fire Protection. Getting the Claim Against The Subcontractor Right
Correct Procedure It is not always the case that claims when settled follow a logical method
involving precise calculation. Towards the end of lengthy negotiations
horse trading often becomes the preferred method of arriving at a lump
sum walk away settlement figure. Before putting their signatures to a
settlement agreement main contractors should have in mind their strategy
if appropriate of recovering money from subcontractors whose quality of
work was one of the matters in dispute. If the main contractor is to succeed
in tying in the subcontractor to money included in a settlement with the
employer ideally prior agreement with the subcontractor as to the sum
included should be reached. Failing this the main contractor will have
to demonstrate that any sum included in respect of the subcontractor’s
defective work is reasonable otherwise the main contractor will find recovery
from the subcontractor could prove difficult. |
|
|||