WHEN DOES A VARIATION IN CONSTRUCTION BECOME A SEPARATE CONTRACT?
Variations Clause
Most standard forms of contract include a clause under which the employer
or his representative is able to issue an instruction to the contractor
to vary the works which are described in the contract. A change in shape
of the scheme, the introduction of different materials, revised timing
and sequence are all usually provided for by the variations clause. It
will also usually include a mechanism for evaluating the financial effect
of the variation and there is normally provision for adjusting the completion
date. In the absence of such a clause the employer could be in a difficulty
should a variation to the works be required. The contractor could either
refuse to carry out the work or undertake the work and insist upon payment
on a quantum meruit or fair valuation basis. Calculation of the price
for the extra work applying this method could involve payment well in
excess of the contract rates.
Separate Contract
Even where a contract includes the usual variations clause there may
be circumstances which could lead to additions or changes introduced by
the employer which falls outside the variations clause. Contractors who
find themselves with unattractive contract prices would find it to their
advantage to be able to argue that a change introduced by the employer
fell outside the variations clause thus leaving the way open to argue
that payment for the change should be on a quantum meruit or fair valuation
basis.
This situation arose in the UK case of Blue Circle Industries v Holland
Dredging Co (1987). The works involve dredging in Larne Lough in Ireland
to enable larger vessels to dock. The tender referred to the dredged material
being deposited in areas approved by the public authorities, the intention
being to discharge the material excavated in suitable areas in the lough.
Resistance to the plan came from several quarters including the Larne
Harbour Board and as a result an alternative plan was agreed to use the
excavated material to form an artificial bird island. It was argued by
the contractor that this was not a variation to the works within the confines
of the contract but a separate contract in its own right.
The decision in Thorn v Mayor and Commonalty of London a case heard way
back in 1876 influenced the court. In this case it was held that if the
additional or varied work were so peculiar, so unexpected and so different
from what any person reckoned or calculated upon to such an extent that
it is not contemplated by the contract then it would constitute a separate
contract. The judge in the case considered that the construction of the
bird island was wholly outside the scope of the original dredging contract
and therefore constituted a separated contract.
Experience In The USA
The position in the USA is similar but more developed. It addresses a
situation where a large number of changes are instructed which individually
fall within the ambit of the variations clause but collectively have the
effect of completely changing the scope of the works. This situation is
referred to as either abandonment or cardinal change and deals with the
situation where the employer makes excessive changes to a project beyond
what the parties reasonably could have anticipated at the time the contract
is entered into. Courts will look at a number of factors in helping to
decide whether the changes have been excessive. The starting points are
the size, complexity and expected duration of the contract. Other factors
to be considered are the number of changes, how many changes were anticipate
when the project started, the magnitude of the work involved in the changes
and the length of time in which such changes were made.
There is no required intention on the part of the employer to abandon
the contract by introducing excessive changes; this will often be implied
as a result of constant interference or change. If the parties ignore
the procedural provisions of the contract with regard to variations this
could help influence the court into accepting that abandonment has occurred.
Conclusion
It is difficult to be hard and fast as to when additional or changed
work will constitute a separate contract or convert the contract the parties
entered into a different one. Courts in the USA seem to be more sympathetic
to the contractors case for abandonment or critical change than
in most other countries. Courts and arbitrators in the UK and like jurisdictions
find themselves in the long grass when trying to decide what is due if
payment is to be on a quantum meruit or fair valuation basis. They feel
more comfortable in dealing with additions or changes priced at contract
rates and are inclined to play it safe in holding that the facts as presented
have not resulted in a separate contract. Employers who are perhaps starting
to feel uneasy about the prospect of the USA attitudes creeping into the
thinking of judges or arbitrators could give consideration to rewording
the variations clause to give a wider definition of additions and change.
Back to News Articles Home
|