MANAGERS COSTS RECOVERABLE IN CLAIMS AGAINST SUPPLIERS
Supply Side
Suppliers of materials and equipment are usually resistant to claims
received from a buyer for faulty goods which includes anything other than
straightforward replacement or remedial costs. The Scottish case of Euro
Pools v Clydeside Steel Fabrications Ltd arose out of the purchase of
filtration equipment for pubic swimming pools which were being constructed
at Burntisland and East Molesey in Surrey and involved a dispute concerning
managerial costs associated with the supply of defective equipment.
Euro Pools had a contract with the main contractor for the swimming pool
water management systems for both contracts. Clydeside supplied the filtration
equipment. The purpose of the filtration equipment is to remove impurities
from the water which has to pass through sand and gravel filter media
inside a large tank shaped like an upright cylinder. The water is warm
and chlorinated and as such is corrosive. To prevent corrosion the tanks
are lined with high build epoxy. It was Clydesides duty under its
contract to design filtration equipment which was fit for its purpose
Defective Goods from Suppliers
Some two months after commissioning it was discovered that the protective
lining inside the tanks had failed. Clydeside disputed that there was
any corrosion and Euro Pools managing director who became involved in
the matter found that in fact there was widespread corrosion. Fenwick
Inspection Services Ltd were appointed by Euro Pools to provide advice
on the remedial works which were principally carried out by Tyneside Filtration
and Engineering Services Ltd. Some of the work involved in decommissioning
and recommissioning the filters was carried out by Euro Pools own employees.
Claims were levied by Euro Pool against Clydeside in the sum of 8119
pounds in respect of the Burntisland pool and 12106 pounds for the one
at East Molesey. These claims included the cost of engaging Tyneside Filtration
and Engineering Services and Fenwick Inspection together with a sum in
respect of the time spent by Euro Pools managing director in attending
meetings and dealing with substantial correspondence and telephone calls
in organising and co-ordinating repairs. The cost of Euro Pools engineers
who were involved in the resolving the problem was also included in the
claim.
Remedy
Clydeside attacked the claim on the basis that the costs were remedial
costs sustained under the contract with the main contractor. This seems
an odd argument as the costs were incurred as a result of the faulty equipment
they supplied and was quickly dismissed by the judge. The second argument
has a little more substance. Clydesides case was that Euro Pools
entitlement was to recover any actual cost or loss which resulted as a
direct consequence of the defective equipment.
The managing director and engineers were not employed specifically in
relation to the remedial works and therefore their salaries would have
been paid in any event. This being the case Euro Pool had sustained no
ascertainable loss as a result of the defects. It was accepted however
that fuel costs in relation to visits to the swimming pools were an extra
cost which could be recovered.
The judge again was not impressed. His view was that a managing director
will normally be expected to devote the whole of his time in the affairs
of his employer involving company strategy, searching for new markets
and the developments of new products. If he is diverted from these tasks
to deal with remedial equipment obtained from a supplier this will deny
him the time which he would otherwise have spent on his normal tasks and
as such represents a loss to his employer. The same principle applies
to engineers in that time spent on remedial work represents time which
could have been profitably spent on their employers work.
Quantification
The claim included the basic salaries of the managing director and engineers
plus a mark up for overheads. The mark up for the engineer was 350% added
to the hourly charge with a 50% increase on top of the managing directors
salary costs. The percentage addition for the engineers was said to be
the usual mark up for daywork in the industry and the addition in respect
of the managing director was intended to represent a reasonable amount.
The judge accepted in principle that overheads are rightfully to be included
in the claim. He felt that a contribution should be made to cover such
matters as the cost of maintaining business premises, computer systems,
head office and accounting staff, salesmen, estimators and general technical
support.
Looking Forward
With decisions such as this one the question normally asked is whether
it is likely to have any affect on the manner in which disputes arising
out of construction contracts are resolved in the future. The recovery
of managerial costs was the subject of a dispute in the case of Tate and
Lyle v Greater London Council. In this case the claim was rejected due
to lack of proper supporting evidence but the principle however was in
general terms accepted. The Euro Pools case moved the situation on a notch
as the court became involved with reinforcing the principle and in addition
offered a view on the method of calculation.
This case however may be a clarion call for suppliers to review the limitation
clauses in their standard terms to ensure that liability extends only
to physical remedial costs and excludes managerial time. Such a limitation
however to accord with The Unfair Contract Terms Act and therefore be
effective would have to be shown to be reasonable.
Back to News Articles Home
|