Importance of contractor progress payment terms
CASH IS KING
Getting The Tender Right
It has been said that an army marches on its stomach. Contractors and
subcontractors in the construction industry run on cash. Lord Denning
many years ago made the oft repeated phrase that cash flow is the lifeblood
of the construction industry and this sentiment is still relevant today.
Estimators when preparing tenders usually concentrate on building profits
into the price. Of equal importance is the amount of working capital required
to fund the contract and the need to keep the amount to a minimum. The
payment terms are therefore crucial to every contractor and subcontractor.
Certification and payment should be the subject of careful strategy and
planning.
Mobilisation payments are common on overseas projects and should be considered
by estimators on home based contracts and proper provision where appropriate
included in the tender. The cost of manufacture is often greater than
onsite erection but many standard contracts do not provide for certification
and payment until the goods have been delivered to site. The reasons are
historic in that when these contracts were first drafted many years ago
there was very little offsite manufacture and fabrication. Many contracts
drafted more recently however recognise that there are substantial costs
which may be incurred prior to a start being made on site. The same principle
applies to the design costs.
Many years have passed since Architects designed work undertaken by specialist
subcontractors. Collateral design warranties became widespread due to
the design of specialist installations being passed down to the specialist
subcontractor. These early design costs need to be recovered as soon as
possible usually long before onsite erection has commenced. When preparing
a tender it is therefore essential for proper provision to be made for
certification and payment for design and offsite manufacture when the
costs are incurred and not many weeks of months later. The specialist
subcontractor needs to stand firm when these provisions are challenged
by the main contractor or the Employers consultants.
In contract negotiations price and performance are usually of more importance
to the Employer as the money to pay for the project has usually already
been allocated and it is a matter of timing as to when it is called down.
Improving On Going Contractor Payments
Most standard forms of contract provide for monthly payments which are
based upon the value of work completed in the previous month. The process
of valuing work on a monthly basis can be time consuming and therefore
in recent years there has been a move to introduce milestone or stage
payments whereby a pre-agreed sum is paid only when work has reached a
certain stage or milestone. This information is usually provided at tender
stage by the tenderer who needs to invest time and effort into ensuring
that the stage or milestone payment plan is calculated to maximise cash
flow. Employers who use the normal JCT forms of contract are rarely advised
of the risk allocation which is prescribed in the contract.
No provision is usually made in Employers budgets for the possibility
of cost overrun. When as a result of variations and delay and disruption
claims this becomes a reality the payment shutters come down and receiving
money for this type of item becomes very difficult. Contractors and subcontractors
often do nothing to help themselves.
Final valuation of variations and delay and disruption claims isnt
given a priority status and can be very damaging to cash flow if left
until the work on site has been completed. Time is often saved if variations
are finally valued at the time the work is being carried out and delay
and disruption claims at the time when these events occur. Getting the
additional cost of variations and delay and disruption claims agreed and
paid has created a problem for contractors and subcontractors for as long
as anyone can remember.
There is no need to suffer for very long in view of the provisions of
the Construction Act 1996 which came into force on 1st May 1998. Adjudication
which is provided for under the Act is now available at any time to both
parties to a construction contract. It takes less than a week to have
an adjudicator appointed and his or her decision must be published within
28 days thereafter. With a few exceptions these decision are enforceable
by the Courts. In excess of 6000 adjudications have been heard since the
Act came into force, the majority of which have been commenced by specialist
subcontractors who consider they have been underpaid. Often the threat
of adjudication is sufficient to enable meaningful negotiations to get
under way.
Remedies For Late or Non-payment
The Construction Act has been a blessing to specialist subcontractors.
Not only does it provide facilities for referring disputes to adjudication
but it outlaws pay when paid clauses. These clauses allow the main contractor
to delay payment to the subcontractor until the money is received from
the Employer and to avoid payment to the subcontractor entirely if the
money isnt received from the Employer. Since the coming into force
of the Act the only pay when paid clause permitted is in respect of non-payment
due to the insolvency of the Employer. A further benefit included in the
Act provides that if payment is not forthcoming in accordance with the
contract terms the contractor or subcontractor may subject to proper written
notice suspend work until payment has been received. When money is in
short supply often the companies who threaten to suspend work are the
ones who receive payment first particularly if the work is on the critical
path. If payment is made late interest becomes due on the outstanding
money in accordance with Late Payment of Commercial Debts (Interest) Act
1998 which applies to all contracts as from 1st November 2002. The rate
of interest payable is 8% above bank minimum lending rate unless the contract
itself provides a substantial remedy for late payment. This contractual
remedy to be regarded as substantial would have to be in the region of
an 8% interest rate. If properly applied these statutory provisions can
often substantially improve a specialist subcontractors cash position.
Benefits of Partnering
It has been argued that many of these problems are removed on Partnering
Contracts. If this is the case many specialist subcontractors are still
still waiting for the benefits to filter down and in the mean time may
prefer to apply the Cash is King policy.
Back to News Articles Home
|